Sunday, May 3, 2015

Ready for concrete

Rebar installed (two near the bottom of the footer - one near the top), hydronic heating line installed (perimeter only), vapor barrier put in place, wire mesh laid down, slab sectioned off and pre-pinned for concrete. Hoping to pour within the next two weeks.

I still need to build the bolt patterns and get those installed in to the correct locations.

2" (50mm) foam insulation for slab perimeter



One loop of heat for the perimeter

Flat wire

South East corner of the building will contain a small bathroom, power panel and hydronic heating components


I'm no farmer, but I believe they are putting some pesticide into the soil before planting feed corn. 
Power supply for sump pump

South West Corner of the house looking North West

Working on getting the slab sectioned off for separate pours

Middle section will be the first poured, then the section on the far right (North)

Rebar tied off to wire mesh near top of slab