Wednesday, August 19, 2015

Service Door & Base flange

No pics, but I did get the service door frame installed and got most of the base flange bolted down to the concrete. I also got the sheet angle installed on the upper ends of the rafter edges. This will provide a surface for the end sheets to attach to.

I did end up like 50' short on the sheet angle, so I've got to get some made locally to accommodate.

Insulation is scheduled to arrive Monday or Tuesday, so the walls should be up next week.